The Rs5.27-billion project, which started in June 2013, was scheduled to be completed by 2017. “As the project works have been affected for nearly a year, we expect it will be completed by 2018,” said Pradip Shrestha, spokesperson for the Division Road Office, Lalitpur. “The works have picked up pace since January.”
Under the project, the existing two-lane road will be expanded to eight lanes with separate carriageways, service tracks, green belts, bicycle lanes and footpaths on either sides.
Shrestha said the project plans to complete construction of four bridges at Balkumari, Balkhu, Kalanki before this year’s monsoon. After that, the project will start blacktopping works and complete three overhead bridges at Koteshwor, Dhobighat and Satdobato.
According to officials at the Kathmandu Ring Road Improvement Project, work of opening track on either side of the road is more than 50 percent complete. Likewise, 40 percent of wall construction, 30 percent of drainage construction and 40 percent of pavement construction works have b
Loading...
Post a Comment